ONGOING PROJECTS
MASTER PLAN ROADS:
| SL.NO. | Name of the work | Estimate Cost Rs. Crores | Present status | Probable Date of completion |
|
MASTER PLAN ROADS: |
|
|
|
1 |
100’-0” wide approach road to Madhurawada IT SEZ. - 0.9Km. |
1.68 |
Work completed |
|
2 |
100’-0” wide road from Boyapalem Jn., on NH-5 to Kapulauppada Village – 3.2 Km |
2.10 |
Work Completed |
|
3 |
80’-0” wide road connecting Boyapalem 100’-0’ road and Kapulauppada – VUDA layout - 0.80 Km |
1.57 |
80% of the work
completed |
31-08-2011 |
4 |
80’-0” wide road connecting P.M.Palem and NH-5 near Car shed junction at Madhurawada - 1.80 Km |
3.60 |
Work commenced and held up for want of shifting of water supply and power lines by GVMC and APEPDCL. At present shifting work in progress. |
30-09-2011 |
5 |
80'-0" wide road from Navodaya School Jn. to Devimetta Hill at Kommadi - 1.70 Km |
4.49 |
25% of the work completed and work is in progress |
30-09-2011 |
6 |
100’-0” wide road connecting NH-5 at Marikavalasa jn. and Harita Housing project junction – 3.2 Km. |
9.10 |
25% of the work completed and work is in progress |
30-09-2011 |
7 |
100'-0" wide road connecting NH-5 at Yendada and Rushikonda VUDA Layout via Law College |
9.10 |
25% of the work completed and work is in progress |
30-09-2011 |










-
COMMERCIAL CUM OFFICE COMPLEX AT SEETHAMMADHARA
-







-
WORLD TELUGU CULTURAL AND HERITAGE MUSEUM ON KAILASA HILL



1) APPROACH ROAD TO MADHURAWADA IT SEZ
2) 100’ WIDE ROAD CONNECTING NH-5 AT MARIKAVALASA JN.
NAVODAYA SCHOOL JN. TO DEVIMETTA HILL AT KOMMADI
| SL.NO. | Name of the work | Estimate
Cost Rs. Crores |
Present status |
Probable Date of completion |
II |
HOUSING |
|
|
|
1 |
Construction of Housing Project at Madhurawada Phase-I (Harita) |
123.20 |
Casting of slabs completed for 270 units out of total 710 units , Masonry 56 units completed and remaining work in progress. |
31-5-2012 |
2 |
Construction of Row Housing Scheme at Rushikonda. |
22.20 |
Main Building works including infrastructure works completed. Layout electrification work and landscaping works are in progress. 90% work completed. |
15-09-2011 |
III |
SHOPPING COMPLEXES: |
|
|
|
1 |
Construction of Modern Shopping Complex at Seethammadhara, Visakhapatnam |
6.00 |
Earth work excavation for foundations nearing completion |
31-3-2012 |
IV |
SITES & SERVICES / PLOTTED DEVELOPMENT SCHEME |
|||
1 |
Providing Infrastructure facilities to Land Pooling layout (Ozone Valley) Phase-I(Acs100.00 Cts.) |
18.00 |
Formation of main Arterial roads with BT surface and internal roads with quarry rubbish has been taken up and completed with an estimates cost of Rs.427.00 Lakhs. At present bridge work in progress. Tenders finalized for construction of SW drains and water supply distribution works amounting to Rs.760.00 Lakhs |
30-6-2012 |
2 |
VUDA Cyber Valley Layout at Madhurawada (Acs.22.00 Cts.) |
5.50 |
Initially formation of Quarry rubbish roads have taken up and completed recently with an estimated cost of Rs.130.00 Lakhs. Estimates under finalization for balance infrastructure facilities. |
30-6-2012 |
3 |
Providing Infrastructure facilities to S.No.1/p of Yendada Layout (Acs.17.00 Cts.) |
2.70 |
20% of the work competed. Water supply works in progress. |
30-9-2011 |
V |
PARKS |
|||
1 |
Development of Dr. Y.S. Rajasekhara Reddy Park at Old City Central jail compound (Foundation stone laid by Hon’ble Chief Minister of A.P) (Acs.20.42 Cts.) |
25.00 |
Initially compound wall with ornamental grills work taken up with an estimate cost of Rs. 180.00 Lakhs. Dr. YSR Bronze statue kept ready for erection. 80% of the work completed. Plans & Designs for Internal Development are under finalization. |
30-6-2012 |
‘HARITA’ PHASE-I HOUSING PROJECT AT MADHURAWADA
VUDA SENIOR CITIZENS’ CENTRE CUM GUEST HOUSE
OZONE VALLEY AT PARADESIPALEM
CYBER VALLEY AT MADHURAWADA
DR.Y.S.RAJASEKHARA REDDY PARK AT OLD JAIL AREA
| SL.NO. | Name of the work | Estimate
Cost Rs. Crores |
Present status |
Probable Date of completion |
VI |
OTHER PROJECTS |
|
|
|
1 |
Construction of Telugu Heritage and Cultural Museum on top of Kailasa Hill. |
4.43 |
Main building work completed. Interior finishes in progress. Internal episodes and Artifacts are under finalization by WTF. |
30-3-2012 |
2 |
Construction of Library Building at Sector - II of MVP Colony |
0.35 |
85% of the work is completed. Finishes in progress. |
15-8-2011 |
3 |
Proposed construction of New Block at Mrs. AVN College Premises. |
1.00 |
Tenders received and under finalization. |
31-3-2012 |
4 |
Construction of VUDA Senior Citizen Center & Guest house in Kirlampudi Layout |
5.60 |
BOQs under finalization. Tenders to be invited. |
31-8-2012 |
|
Bheemili Area: |
|||
1 |
Renovation of West block of Junior College at Bheemili in connection with 150 years Celebrations of Bheemili Municipality (Heritage building) |
0.37 |
Work completed recently |
|
2 |
Formation of 40’-0” wide road connecting Visakha- Bheemili Beach road and SOS Village near Bheemili. |
0.92 |
Work completed recently |
30-6-2012 |
3 |
Construction of Pylon (Galimeda) with sculpture work in connection with 150 years celebrations of Bheemili Municipality |
0.20 |
Work commenced recently and in progress. |
31-10-2011 |
4 |
Construction of Indoor Stadium at Bheemili in connection with 150 years Celebrations of Bheemili Municipality. |
2.50 |
Plans & Designs are under finalization |
30-9-2012 |
| SL.NO. | Name of the work | Estimate
Cost Rs. Crores |
Present status |
Probable Date of completion |
|
Vizianagaram Area: |
|
|
|
1 |
Construction of SW Drains from Balaji complex to Thotapalem at Vizianagaram |
0.50 |
Work completed recently |
--- |
2 |
Widening and formation of 50’-0” road connecting Balaji complex to Thotapalem at Vizianagaram. |
0.97 |
Work entrusted arrangements are being made to begin the work. |
31-10-2011 |
|
Anakapalle Area: |
|||
1 |
Construction of Kalyanamandapam at Munagapaka |
0.60 |
Building work completed. Finishes in progress. |
31-8-2011 |
2 |
Construction of Municipal Office Building |
1.30 |
Work could not be commenced due to site dispute |
-- |
|
Srikakulam (Extended area) |
|||
1
|
Formation of 80’-0” wide Master Plan Road connecting Arasavalli Junction and Collectorate at Srikakulam. |
5.45 |
Forming embankment is in progress for part of the road 25% of the work completed so far .Progress of the work hampered due to recent monsoon rains. |
30-9-2011 |
| Sl.No | Project |
Terms of |
Status of the |
Amount remitted to |
Remarks |
Project |
1 |
Integrated Housing Project - PPP (JV) in Bulk lands of Tarakarama Nagar Township Layout measuring Ac.50.00 Cts In S.No. 336/P of Madhurawada. M/s. Radiant Developers (P) Ltd., Hyderabad. | Agreement entered on 27.8.2005. Independent Houses, Row Housing, Duplex Houses & Apartments with amenities like Club House, Convenient Shopping, etc., Rs.13.00 Crores to be paid by the developer as MGS (or) 7.5% of Gross Revenues on Sale Proceeds whichever is higher. | An Expert Committee was appointed by the Government for finalization of the DPR. Government was informed about the proceedings of the Meeting enclosing therewith DPR for approval. Expert Committee remarks submitted to Government. As per the directions of Government further action is being taken. | Rs.218.80 Lakhs was paid towards Development charges. | Ground leveling works are being carried-out. | Integrated Housing Project - PPP (JV) in Bulk lands of Tarakarama Nagar Township Layout measuring Ac.50.00 Cts In S.No. 336/P of Madhurawada. M/s. Radiant Developers (P) Ltd., Hyderabad. |
2 |
Housing Project (Gated Community Housing) - PPP (JV) in Bulk lands of Yendada & Madhurawada measuring Ac. 80.00 Cts in S.No.1/p of Yendada & S.No.386/p (v) of Madhurawada (v) M/s. Global Entropolis Asia Pvt. Ltd., Hyderabad. . | Agreement entered on 23.12.2006. As per the pre-closure option, the developer has remitted Rs. 242.29 Crores towards project development revenues. LIG, MIG, HIG, Villas, School, Poly Clinic, Convenient Shopping, Community Hall / Club House. | The Developer has obtained required clearances viz., environmental clearance, Airport & Fire Clearances. Building Plans approved. Work is under progress. | Rs.1.00 Crore towards Non-refundable Project Development fee. Rs.242.29 Crores towards project revenues as pre-closure has been remitted to Government Budgetary Support. | VUDA is keen for early completion of the project (36 Months) i.e., 2012. | Housing Project (Gated Community Housing) - PPP (JV) in Bulk lands of Yendada & Madhurawada measuring Ac. 80.00 Cts in S.No.1/p of Yendada & S.No.386/p (v) of Madhurawada (v) M/s. Global Entropolis Asia Pvt. Ltd., Hyderabad. |
3 |
Commercial Complex with IT Space at Gandhi Place, Siripuram (BOT Basis) measuring 6540.00 sq. yards in TSNo.85/1A of Waltair Ward M/s. Vaibhav Sky Scapes Pvt. Ltd., Visakhapatnam | Agreement entered on 16.2.2008. Lease Period 33 Years. Revenue Sharing Model by means of lease rentals i.e., 5% of Market Value of the land (Rs.70.90 Lakhs per annum) and periodical increase of 5% every year + Additional Development Premium (Rs.106 lakhs per year (or) on 3% of Gross Revenue whichever is higher). | Statutory Building plans approval accorded and ground leveling works are in progress. Lease rentals and ADP being paid by the developer regularly. Ground leveling works are under progress. | Rs.304.77 Lakhs was paid so far towards Lease Rent, Development fee. BG of Rs.50.00 lakhs paid towards Development and Construction Guarantee. | The Agency was requested to speed up the work. | Commercial Complex with IT Space at Gandhi Place, Siripuram (BOT Basis) measuring 6540.00 sq. yards in TSNo.85/1A of Waltair Ward M/s. Vaibhav Sky Scapes Pvt. Ltd., Visakhapatnam |
4 |
Shopping Mall with Multiplex (Old Balaji Complex Site), Vizianagaram. (BOT Basis) measuring 3597.12 sq. yards M/s. Ambica Empire Pvt. Ltd., Eluru | Agreement was entered on 11.4.2008. Lease Period 33 Years. Lease Amount : Rs. 5.21 Lakhs with 5% escalation Per Annum. ADP: Rs.15.12 lakhs per year (or) on 3% of Gross Revenue whichever is higher A non-refundable Project Development Fee of Rs.8.63 lakhs Shops, Anchor shops, Showrooms, Food Courts, Multiplex with 3 Screens & Family Entertainment Centre. | Statutory Building plans approved. Work nearing completion. Lease amounts being paid regularly by the developer. | Rs.20.40 Lakhs paid towards Lease rent and Project Development Fee. | Work nearing completion Instructions issued to the Agency to complete the work within three months. | Shopping Mall with Multiplex (Old Balaji Complex Site), Vizianagaram. (BOT Basis) measuring 3597.12 sq. yards M/s. Ambica Empire Pvt. Ltd., Eluru |
5 |
Ultra Modern Layout at Dakamarri PPP (JV) Extent - Ac.97.07 Cts In S.No.348 of Dakamarri (v) M/s. Vensar Constructions Company Ltd., Hyderabad | Agreement entered on 19.3.2008. Ultra-modern Layout with High-quality living conditions and best of the amenities such as BT Roads, Open Drains, Water Supply Arrangements, Layout Electrification, Avenue Plantation, Filter Bed & Avenue Plantation, Play Equipment for Children in the Parks and Compound wall all around the open spaces etc. | The possession of the site has been handed over to the developer. The developer finalized the concept layout plan as per the norms. The draft variation proposals approved by Government. Revised drawings as per prevailing norms to be submitted by the Developer. | Performance Guarantee amount of Rs.1.55 Crs paid by way of BG. A non-refundable one-time Project Development Fee of Rs.18.50 Lakhs. | Ultra Modern Layout at Dakamarri PPP (JV) Extent - Ac.97.07 Cts In S.No.348 of Dakamarri (v) M/s. Vensar Constructions Company Ltd., Hyderabad | Agreement entered on 19.3.2008. Ultra-modern Layout with High-quality living conditions and best of the amenities such as BT Roads, Open Drains, Water Supply Arrangements, Layout Electrification, Avenue Plantation, Filter Bed & Avenue Plantation, Play Equipment for Children in the Parks and Compound wall all around the open spaces etc. |
6 |
Multi-use Commercial complex at K.L. Rao Nagar, Gajuwaka measuring 5,253.33 Sq.Yards in S.No. 64/P of Pedagantyada (V) | -- | Bid-Process for the Project is under progress. | -- | Multi-use Commercial complex at K.L. Rao Nagar, Gajuwaka measuring 5,253.33 Sq.Yards in S.No. 64/P of Pedagantyada (V) |
Vizag - Bheemili Beach Road
Project stretch - 25.50 Kms.
Project Cost - 60 Cr.
Funding - VUDA, R & B @ 50:50
4 lane road with median,
footpaths & electrification

0 - 2 Kms developed by VUDA initially.
Development of 6 - 15 Kms stretch
is under progress.
Design features include eco-friendly
in nature & Tourism concepts.

Widening & improvement of Master Plan roads
Roads completed |
Rs. In Crs. |
R3-100' wide road connecting Beach Road & NH-5 via Vignan School - 7.2 Kms. |
25.45 |
R2-100' wide road connecting Marikavalasa Road connecting NH-5 to Beach Road - 3.3 Kms |
11.80 |
R7-80' wide road connecting NH-5 via Law College to Mithilapuri Road- 3.0 Kms. |
11.00 |
Demarcation Completed |
Rs. In Crs. |
R4 - 60' wide ghat road on Kailasa Hill (Strengthening & Improvement) - 2.0 Kms |
4.60 |
R8 - 100' wide road connecting Beach Road & NH-5 via Kapuluppada & Boyyapalem - 6.0 Kms |
21.25 |
R10 - 80' wide road connecting Dorathota road Via Vellanki to NH-5 - 2.00 Kms |
7.00 |
R11 - 80' wide road connecting Duvvada Station via Narava to Gopalapatnam - 10.0 Kms. |
35.15 |
R12 - 100' wide road connecting Bheemili to NH-5 via Rajula Tallavalasa - 5.0 Kms. |
18.90 |
R14 - 80' wide road connecting Nidigattu to Nerallavalasa - 3.5 Kms |
23.50 |
R15 - 80' wide road connecting Sontyam Padmanabham - 10.0 Kms. |
11.50 |
R15 - 80' wide road connecting Sontyam Padmanabham - 10.0 Kms. |
33.35 |
Road works under progress |
Rs. In Crs. |
R1-100' road connecting Appughar, Visakhapatnam to Bheemili Municipal Office Jn., Beach Road. - 24.0 Kms. |
100 |
R6-80' wide road connecting Yendada 'Y' Junction to Rushikonda Layout Road - 2.5 Kms. |
8.60 |
R7-80' wide road connecting NH-5 via Law College to Mithilapuri Road- 3.0 Kms. |
9.50 |
R9-100' wide road connecting NH-5 Madhurawada to Bakkannaplem via S.No.56 - 2.0 Kms |
7.85 |
R19-100' wide road connecting Duvvada to Aganampudi - 4.0 Kms. |
14.95 |
Demarcation Completed |
Rs. In Crs. |
R16 - 80' wide road connecting Parawada to Anakapalli - 12.0 Kms. |
38.35 |
R17 - 60' wide road connecting Pulagalapalem to Gurrampalem - 4.0 Kms. |
12.30 |
R18 - 100' wide road connecting Duvvada to Sabbavaram via Asakapalli Jn. (Lankalapalem Road) - 11.0 Kms. |
40.65 |
R20 - 100' wide road connecting Lankalepalem to Sabbavaram - 9.0 Kms. |
32.55 |
Housing Projects
Yendada & Madhurwada

PPP Model
Total extent of Site : Ac. 80.00
Estimated Cost : Rs.581.20 Crores.
Work Entrusted to M/s. Jurong & ABS Infrastructure (India) Pvt., Ltd., Bangalore.
4235 units and provides Housing for 25,000 population
72 Lakhs Sft built up area
Villas, HIG, MIG, LIG & Flats
- School
- Poly Clinic
- Convenient Shopping
- Community Hall / Club House
Ground work to be started.
Vepagunta Housing

PPP Model
Total extent of Site : Ac. 55.00
Estimated Cost : Rs.226.50 Crores.
Work Entrusted to M/s. L&T and Vision Ventures Pvt., Ltd.,Hyderabad
689 units and provides Housing for 3500 population
15.50 Lakhs Sft built up are
- Villas, Flats - School
- Poly Clinic
- Convenient Shopping
- Community Hall/ Club House
Row Housing Project

Rushikonda Layout, Madhurwada, Visakhapatnam
Total extent of Site : Ac. 6.78Cts.
88 units and provides Housing
for 500 population Row-Housing of East & West facing buildings - Duplex type
- Crèche - Central park
- Convenient Shopping
- Community Hall/ Club House
50% work Completed
Housing Project

(Design, Build & Contract Model) Madhurwada, Visakhapatnam
Total extent of Site : Ac. 40.00Cts.
Project Cost : Rs.265.77cr
2024 units and provides Housing for 10,000 population
Group-housing of HIG & MIG
High-rise residential apartment buildings of 11 floors
School, Poly Clinic, Convenient Shopping,
Community Hall/ Club House
Work to be grounded.
Gandhi Place, Siripuram

BOT Basis
Total extent of Site : 6540 Sq.Yds
Estimated Cost : Rs.21.00 Crores.
Work Entrusted to M/s. Vaibhav Empire Pvt Ltd.,
A Huge commercial space with Sub cellar, Cellar, G+8 Floors 142500 Sft built up area
Parking, Retail Shopping, Food courts & Restaurant,
IT Incubation space, Services
Apartments and Guest House.
Ground work to be started.
IT Layouts at Rushikonda

Total extent of Site : Ac. 141.52
(Hill No.-2 & 3)
Construction Work of IT
Total No. of Plots proposed for IT Agencies : 25 Nos.
Total Plots allotted : 19 Nos.
Building Plans Approved : 13 Nos.
Building Plans received for scrutiny : 01 Nos.
Buildings are in Progress.
Yet to submit building plans : 05 Nos.
Vacant Plots : 06 Nos.
Buildings are in progress.